Step 1

Display the Details of the Workflow for which you want to specify a critical endpoint.

Step 2

Click the Critical Endpoints tab. The critical endpoint list displays a list of any existing critical endpoints for that task.

Step 3

Click the . Critical Endpoint Details displays:
 

Step 4

Select a Task from the drop-down menu to be a Critical Endpoint in the workflowEnable Late Start or Late Finish to override task level time option conditionslevel Late Start and Late Finish conditions. If you leave the Late Start and Late Finish options unchecked, the task-level conditions will remain unchanged

Step 5

Click the  to save the record.

...