Anchor | ||||
---|---|---|---|---|
|
Issue a Command Against a Single Task Instance
...
Anchor | ||||
---|---|---|---|---|
|
Issue a Command Against a Single Task Instance
...
If you want to receive a confirmation message after issuing a command but before the command is performed, set the System Default Confirm Task Instance Commands Universal Controller system property to Yes (the default is No).
For example:
Issue a Command Against a Task Instance within the Workflow
Step 1 | Right-click the task instance to display a pop-up menu of commands appropriate for the selected task instance. |
---|---|
Step 2 | Click Commands and then click the command that you want to issue against the selected task instance. |
For example:
Issue a Command Against the Workflow Task Instance
Step 1 | Right-click the Workflow Monitor canvas to display a pop-up menu of commands appropriate for the workflow task instance. |
---|---|
Step 2 | Click Commands and then click the command that you want to issue against the workflow task instance. |
For example:
Anchor | ||||
---|---|---|---|---|
|
...
Step 1 | From the Automation Center navigation pane, select Tasks > <type of task>. The Tasks list for that task type displays. | |||||
---|---|---|---|---|---|---|
Step 2 | Either:
An Action menu displays. | |||||
Step 3 | Select either:
| |||||
Step 4 | To view Details about running task instances, select Task Instances > Activity from the Automation Center navigation pane and click on the task instance. |
...
Step 1 | Select the task you want to launch. |
---|---|
Step 2 |
Anchor | ||||
---|---|---|---|---|
|
...
Step 1 | Display the task you want to launch. |
---|---|
Step 2 | Access the Action menu. |
Step 3 | Select Launch Task with Variables.... The Launch Task (with Variables) dialog displays. Any variables attached to this task automatically are displayed in alphabetic order (a-z). |
Step 4 | As needed, set the variable values or add new variables. |
Step 5 | If you want to put the task instance in held status when the task is started, select Hold on Start. A Hold Reason field then displays which allows you to enter information about why the task will be put on hold when it starts. |
Step 6 | If the task is a Workflow (as shown here), and: Time Zone lets you select a time zone for this specific launch of the Workflow so that it runs, and evaluates both Run Criteria and Execution Restrictions, according to that time zone. |
Step 7 | When you are finished, click Submit. The Controller populates the variables with the values you supplied and launches the task. |
...
When you select to launch a task, a dialog displays that ask you to confirm that task that you want to launch:
You also can launch a task that you have modified without saving the modifications.
When you select to launch a modified but unsaved task (single task only), the confirmation dialog specifies that you are about to launch a task with unsaved modifications:
Anchor | ||||
---|---|---|---|---|
|
...
Step 1 | Select the task instance for which you want to set the priority. |
---|---|
Step 2 | Right-click the task instance and, on the Action menu, select the priority level. |
Step 3 | When the Set Priority command has been executed, the Controller displays the following message at the bottom of the list: |
...