Step 1 | From the Automation Center navigation pane, select Tasks > All Tasks or Tasks > Workflow Tasks. | |||||
---|---|---|---|---|---|---|
Step 2 | Display an Action menu either of three ways:
| |||||
Step 3 | Click Forecast... to display a Forecast dialog. | |||||
Step 4 | Select a Date, Time, Time Zone, and Calendar for when you want to forecast the Workflow (and all of its sub-Workflows, if any).
| |||||
Step 5 | Select a View in which you want to display the Forecast: Workflow or List. | |||||
Step 6 | If you selected Workflow View, a Calculate Critical Path field displays. Enable/disable this field depending on whether or not you want to calculate the Critical Path of the Workflow. | |||||
Step 7 | Click Submit to display the Forecast in the selected View.
If you enabled Calculate Critical Path:
|
...