Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Field Name

Description

General

This section contains general information about the task instance.

Anchor
Instance Name
Instance Name
Instance Name

Name of this task instance.

Instance Number

Include Page
UC69IL:Instance NumberUC69
IL:Instance Number

Description

Include Page
UC71xIL:SummaryUC71x
IL:Summary

Member of Business Services

Include Page
UC69IL:Member of Business ServicesUC69
IL:Member of Business Services

Task

Include Page
UC69IL:TaskUC69
IL:Task

Source Version

Include Page
UC71xIL:Source VersionUC71x
IL:Source Version

Launch Source

Include Page
UC69IL:Launch SourceUC69
IL:Launch Source

Source Instance

Include Page
UC69IL:Source InstanceUC69
IL:Source Instance

Invoked by

Include Page
UC69IL:Invoked byUC69
IL:Invoked by

Anchor
Execution User
Execution User
Execution User

Include Page
UC69IL:Execution UserUC69
IL:Execution User

Calendar

Include Page
UC69IL:Calendar in Task InstanceUC69
IL:Calendar in Task Instance

Time Zone Preference

Include Page
UC69IL:Time Zone PreferenceUC69
IL:Time Zone Preference

Virtual Resource Priority

Include Page
UC69IL:Virtual Resource PriorityUC69
IL:Virtual Resource Priority

Status

This section contains information about the current status of the task instance.

Status

Include Page
UC69IL:StatusUC69
IL:Status

Exit Code

Include Page
UC69IL:Exit Code-Task InstanceUC69
IL:Exit Code-Task Instance

Status Description

Include Page
UC69IL:Status DescriptionUC69
IL:Status Description

Operational Memo

Include Page
UC69IL:Operational MemoUC69
IL:Operational Memo

Evaluation Time

Include Page
UC69IL:Evaluation TimeUC69
IL:Evaluation Time

Critical

Include Page
UC69IL:CriticalUC69
IL:Critical

Wait Until Time

Include Page
UC69IL:Wait Until Time - StatusUC69
IL:Wait Until Time - Status

Queued Time

Include Page
UC69IL:Queued TimeUC69
IL:Queued Time

Anchor
Trigger Time
Trigger Time
Trigger Time

Include Page
UC69IL:Trigger TimeUC69
IL:Trigger Time

Anchor
Launch Time
Launch Time
Launch Time

Include Page
UC69IL:Launch TimeUC69
IL:Launch Time

Anchor
Start Time
Start Time
Start Time

Include Page
UC69IL:Start TimeUC69
IL:Start Time

End Time

Include Page
UC69IL:End TimeUC69
IL:End Time

Duration

Include Page
UC69IL:DurationUC69
IL:Duration

Progress

Number of tasks in the Workflow that are in Success, Skipped, or Finished status / Total number of tasks in the Workflow.

Workflow Details

This section contains assorted detailed information about the task instance.

Show/Hide Skipped Tasks

Include Page
UC69IL:Show Hide Skipped TasksUC69
IL:Show Hide Skipped Tasks

Wait / Delay Options

This section contains specifications for waiting to start and/or delaying on start the task.

Anchor
Wait To Start
Wait To Start
Wait To Start

Include Page
UC69IL:Wait To Start - 6.2.1.0UC69
IL:Wait To Start - 6.2.1.0

Anchor
Wait Time
Wait Time
Wait Time

Include Page
UC69IL:Wait Time - 6.2.1.0UC69
IL:Wait Time - 6.2.1.0

Anchor
Wait Day Constraint
Wait Day Constraint
Wait Day Constraint

Include Page
UC69IL:Wait Day ConstraintUC69
IL:Wait Day Constraint

Anchor
Wait Duration
Wait Duration
Wait Duration

Include Page
UC69IL:Wait DurationUC69
IL:Wait Duration

Anchor
Wait Duration In Seconds
Wait Duration In Seconds
Wait Duration In Seconds

Include Page
UC69IL:Wait Duration In SecondsUC69
IL:Wait Duration In Seconds

Anchor
Delay On Start
Delay On Start
Delay On Start

Include Page
UC69IL:Delay On StartUC69
IL:Delay On Start

Anchor
Delay Duration
Delay Duration
Delay Duration

Include Page
UC69IL:Delay DurationUC69
IL:Delay Duration

Anchor
Delay Duration In Seconds
Delay Duration In Seconds
Delay Duration In Seconds

Include Page
UC69IL:Delay Duration In SecondsUC69
IL:Delay Duration In Seconds

Time Options

This section contains information on time-related specifications for the task instance.

Anchor
Late Start
Late Start
Late Start

Include Page
UC69IL:Late StartUC69
IL:Late Start

Anchor
Include Page
UC69:Started LateUC69:Started Late
Anchor
Started Late Started Late
Started Late
Late Start Type
Late Start Type
Late Start Type

Include Page
UC69IL:Late Start TypeUC69
IL:Late Start Type

Anchor
Late Start Time
Late Start Time
Late Start Time

Include Page
UC69IL:Late Start TimeUC69
IL:Late Start Time

Anchor
Late Start Day Constraint
Late Start Day Constraint
Late Start Day Constraint

Include Page
UC69IL:Late Start Day ConstraintUC69
IL:Late Start Day Constraint

Anchor
Late Start Nth Amount
Late Start Nth Amount
Late Start Nth Amount

Include Page
UC69IL:Late Start Nth AmountUC69
IL:Late Start Nth Amount

Anchor
Late Start Duration
Late Start Duration
Late Start Duration

Include Page
UC69IL:Late Start Duration - NEWUC69
IL:Late Start Duration - NEW

Anchor
Computed Late Start Time
Computed Late Start Time
Computed Late Start Time

Include Page
UC70IL:Computed Late Start TimeUC70
IL:Computed Late Start Time

Anchor
Late Finish
Late Finish
Late Finish

Include Page
UC69IL:Late FinishUC69
IL:Late Finish
Anchor
Finished LateFinished Late
Finished Late
Include Page
UC69:Finished LateUC69:Finished Late

Anchor
Late Finish Type
Late Finish Type
Late Finish Type

Include Page
UC69IL:Late Finish TypeUC69
IL:Late Finish Type

Anchor
Late Finish Offset Type
Late Finish Offset Type
Late Finish Offset Type

Include Page
UC69IL:Late Finish Offset TypeUC69
IL:Late Finish Offset Type

Anchor
Late Finish Percentage Offset ( + )
Late Finish Percentage Offset ( + )
Late Finish Percentage Offset ( + )

Include Page
UC69IL:Late Finish Percentage Offset ( + )UC69
IL:Late Finish Percentage Offset ( + )

Anchor
Late Finish Duration Offset ( + )
Late Finish Duration Offset ( + )
Late Finish Duration Offset ( + )

Include Page
UC69IL:Late Finish Duration Offset ( + )UC69
IL:Late Finish Duration Offset ( + )

Anchor
Late Finish Duration Offset Unit
Late Finish Duration Offset Unit
Late Finish Duration Offset Unit

Include Page
UC69IL:Late Finish Duration Offset UnitUC69
IL:Late Finish Duration Offset Unit

Anchor
Late Finish Time
Late Finish Time
Late Finish Time

Include Page
UC69IL:Late Finish TimeUC69
IL:Late Finish Time

Anchor
Late Finish Day Constraint
Late Finish Day Constraint
Late Finish Day Constraint

Include Page
UC69IL:Late Finish Day ConstraintUC69
IL:Late Finish Day Constraint

Anchor
Late Finish Nth Amount
Late Finish Nth Amount
Late Finish Nth Amount

Include Page
UC69IL:Late Finish Nth AmountUC69
IL:Late Finish Nth Amount

Anchor
Late Finish Duration
Late Finish Duration
Late Finish Duration

Include Page
UC69IL:Late Finish Duration - NEWUC69
IL:Late Finish Duration - NEW

Anchor
Computed Late Finish Time
Computed Late Finish Time
Computed Late Finish Time

Include Page
UC70IL:Computed Late Finish TimeUC70
IL:Computed Late Finish Time

Anchor
Early Finish
Early Finish
Early Finish

Include Page
UC69IL:Early FinishUC69
IL:Early Finish

Anchor
Include Page
UC69:Finished EarlyUC69:Finished Early
Anchor
Finished Early Finished Early
Finished Early
Early Finish Type
Early Finish Type
Early Finish Type

Include Page
UC69IL:Early Finish TypeUC69
IL:Early Finish Type

Anchor
Early Finish Offset Type
Early Finish Offset Type
Early Finish Offset Type

Include Page
UC69IL:Early Finish Offset TypeUC69
IL:Early Finish Offset Type

Anchor
Early Finish Percentage Offset ( - )
Early Finish Percentage Offset ( - )
Early Finish Percentage Offset ( - )

Include Page
UC69IL:Early Finish Percentage Offset ( - )UC69
IL:Early Finish Percentage Offset ( - )

Anchor
Early Finish Duration Offset ( - )
Early Finish Duration Offset ( - )
Early Finish Duration Offset ( - )

Include Page
UC69IL:Early Finish Duration Offset ( - )UC69
IL:Early Finish Duration Offset ( - )

Anchor
Early Finish Duration Offset Unit
Early Finish Duration Offset Unit
Early Finish Duration Offset Unit

Include Page
UC69IL:Early Finish Duration Offset UnitUC69
IL:Early Finish Duration Offset Unit

Anchor
Early Finish Time
Early Finish Time
Early Finish Time

Include Page
UC69IL:Early Finish TimeUC69
IL:Early Finish Time

Anchor
Early Finish Day Constraint
Early Finish Day Constraint
Early Finish Day Constraint

Include Page
UC69IL:Early Finish Day ConstraintUC69
IL:Early Finish Day Constraint

Anchor
Early Finish Nth Amount
Early Finish Nth Amount
Early Finish Nth Amount

Include Page
UC69IL:Early Finish Nth AmountUC69
IL:Early Finish Nth Amount

Anchor
Early Finish Duration
Early Finish Duration
Early Finish Duration

Include Page
UC69IL:Early Finish Duration - NEWUC69
IL:Early Finish Duration - NEW

Anchor
Projected Late
Projected Late
Projected Late

Include Page
UC69IL:Projected Late - 6.9.0.0UC69
IL:Projected Late - 6.9.0.0

Critical Path Options

This section contains Critical Path-related specifications for the task.

Anchor
Calculate Critical Path
Calculate Critical Path
Calculate Critical Path

Include Page
UC69IL:Calculate Critical PathUC69
IL:Calculate Critical Path

Anchor
CP Duration
CP Duration
CP Duration

Include Page
UC69IL:CP DurationUC69
IL:CP Duration

Anchor
CP Duration (Resolved)
CP Duration (Resolved)
CP Duration (Resolved)

Include Page
UC69IL:CP Duration (Resolved)UC69
IL:CP Duration (Resolved)

Anchor
CP Duration Unit
CP Duration Unit
CP Duration Unit

Include Page
UC69IL:CP Duration UnitUC69
IL:CP Duration Unit

Workflow Execution Options

This section contains Execution Restriction specifications for the task if it is within a Workflow.

Anchor
Execution Restriction
Execution Restriction
Execution Restriction

Include Page
UC69IL:Execution RestrictionUC69
IL:Execution Restriction

Anchor
Restriction Period
Restriction Period
Restriction Period

Include Page
UC69IL:Restriction PeriodUC69
IL:Restriction Period

Anchor
Before Date
Before Date
Before Date

Include Page
UC69IL:Before DateUC69
IL:Before Date

Anchor
Before Time
Before Time
Before Time

Include Page
UC69IL:Before TimeUC69
IL:Before Time

Anchor
After Date
After Date
After Date

Include Page
UC69IL:After DateUC69
IL:After Date

Anchor
After Time
After Time
After Time

Include Page
UC69IL:After TimeUC69
IL:After Time

Anchor
Date List
Date List
Date List

Include Page
UC69IL:Date ListUC69
IL:Date List

Statistics

This section contains time-related statistics for the task instance.

Anchor
User Estimated End Time
User Estimated End Time
User Estimated End Time

Include Page
UC69IL:User Estimated End TimeUC69
IL:User Estimated End Time

Lowest Estimated End Time

Include Page
UC69IL:Lowest Estimated End TimeUC69
IL:Lowest Estimated End Time

Average Estimated End Time

Include Page
UC69IL:Average Estimated End TimeUC69
IL:Average Estimated End Time

Highest Estimated End Time

Include Page
UC69IL:Highest Estimated End TimeUC69
IL:Highest Estimated End Time

Projected End Time

System-supplied; projected end time of the task instance, calculated by the Controller based on the projected end time of its predecessor (or the maximum projected end time of all its predecessors, if more than one path exists to that task instance) plus its estimated critical path duration.

Metadata

This section contains Metadata information about this record.

UUID

Universally Unique Identifier of this record.

Updated By

Name of the user that last updated this record.

Updated

Date and time that this record was last updated.

Created By

Name of the user that created this record.

Created

Date and time that this record was created.

Status History

History of all statuses that the task instance has gone through.

Buttons

This section identifies the buttons displayed above and below the Workflow Task Instance Details that let you perform various actions.

Update

Include Page
UC69IL:Update buttonUC69
IL:Update button

Force Finish

Include Page
UC69IL:Force Finish buttonUC69
IL:Force Finish button

Hold


Include Page
UC69
IL:Hold button
UC69
IL:Hold button

Skip

Include Page
UC69IL:Skip buttonUC69
IL:Skip button

Release Recursive

Include Page
UC69IL:Release Recursive buttonUC69
IL:Release Recursive button

View Parent

Include Page
UC69IL:View Parent buttonUC69
IL:View Parent button

View Workflow

Include Page
UC69IL:View WorkflowUC69
IL:View Workflow

Delete

Include Page
UC69IL:Delete buttonUC69
IL:Delete button

Refresh

Refreshes any dynamic data displayed in the Details.

Close

For pop-up view only; closes the pop-up view of this task instance.

Tabs

This section identifies the tabs across the top of the Workflow Task Instance Details that provide access to additional information about the task instance.

Workflow Task Instance

Displays details about this Workflow task instance.

Virtual Resources

Include Page
UC69IL:Task Virtual Resources tab - 6.7.0.0UC69
IL:Task Virtual Resources tab - 6.7.0.0

Exclusive Requests

Include Page
UC69IL:Exclusive Requests tabUC69
IL:Exclusive Requests tab

Step Conditions

Include Page
UC69IL:Step Conditions tabUC69
IL:Step Conditions tab

Notes

Include Page
UC69IL:Notes tabUC69
IL:Notes tab

Anchor
Workflow Editor
Workflow Editor

...

Anchor
Searching For and Adding Tasks
Searching For and Adding Tasks
Searching For and Adding Tasks

Several methods are available for finding tasks:

wildcards

Step 1

Click the Add Task icon. The Task Find dialog displays.
 
Image Removed

Step 2

Click the Add Task icon. The Task Find dialog displays.
 
Image Added

Step 2

Several methods are available for finding tasks:

  • To find a specific task, type the name into the Task name field and click Search.
  • To display a list of tasks whose names match a string, type the string into the Task name field and use one or more wildcards. Wildcard(s) can appear anywhere in the string. For example, to find tasks whose name begins with "Fee", type Fee in the Task name field and click Search.
  • To display a list of tasks of a specific type, such as Windows, select the task type from the drop-down menu and click Search.
  • To display a list of all tasks, select All Task Types (the default selection) from the drop-down menu and click Search.

The Task Find dialog lists the task(s) that match your search criteria.
 

Step 3

To add a task to the Workflow Editor canvas, click the icon to the left of the task and drag it onto the canvas.
 
You can add any task to a Workflow multiple times. To differentiate between multiple additions of the same task in a Workflow, you can assign each of them a unique name used only within the Workflow; the name of the task in the Task Details will not change. To change the name of a task within a Workflow, display the Task Properties menu and select a new name in the name field.

Step 4

Repeat these steps until you have added all the tasks you need.

Step 5

Position the tasks on the canvas as desired. The connections that you will make between the tasks determine the order in which the tasks run, so position the tasks accordingly. For example:
 

Step 6

To close the Task Find window, click the X in the upper right corner. Or, to keep the window open but minimized, click the minimize icon.

...

...

Field Name

Description

Type

User-defined; indicates whether this is providing instructions on when to run or not run the task.
 
Options:

  • Run Criteria - Provides instructions on when to run the task.
  • Skip Criteria - Provides instructions on when to skip the task.

Description

Include Page
UC71xIL:SummaryUC71x
IL:Summary

Task

User-defined; task for which you are specifying run or skip criteria. Select a task from the drop-down list of all tasks in this Workflow.

Vertex ID

Vertex ID of the task selected in the Task field. Each task within a Workflow has a unique Vertex ID, which distinguishes it from other tasks of the same name, if any.

Business Day

If enabled, the task runs or skips on all business days.

Anchor
Holiday
Holiday
Holiday

If enabled, the task runs or skips on holidays.

Anchor
Adjustment - H
Adjustment - H
Adjustment

If Holiday is enabled; Specification for adjusting a Holiday by a less or plus number of days or business days.

Options:

  • -- None --
  • Less
  • Plus

Default is – None --

Anchor
Adjustment Amount - H
Adjustment Amount - H
Adjustment Amount

If Adjustment is Less or Plus; Number of days or business days to adjust a Holiday.

Default is 1.

Anchor
Adjustment Type - H
Adjustment Type - H
Adjustment Type

If Adjustment is Less or Plus; Type of day by which to adjust a Holiday.

Options:

  • Day
  • Business Day

Default is Day.

Specific Day(s) – Sunday through Saturday

If enabled, the task runs or skips on the day(s) you select in the right-hand column.

Anchor
Custom Day
Custom Day
Custom Day

If enabled, the task runs or skips on the day you select in the Custom Day Choice field.
 

Note
titleNote

The Custom Day and Custom Day Choice fields display in the Task Run Criteria Details only if the Custom Day Global Permitted Universal Controller system property is set to true (the default).


Anchor
Custom Day Choice
Custom Day Choice
Custom Day Choice

If Custom Day is enabled, select the custom day for which you are specifying run or skip criteria. Enter the name of an existing Custom Day, select a Custom Day from the drop-down list of all existing Custom Days, or click the Details icon to create a new Custom Day.
 
Only a global custom day can be selected for a Custom Day Choice. Use Complex run criteria to use a local custom day.
 
If a workflow is launched using a calendar which does not contain the custom day specified for the Custom Day Choice, the following applies:use a local custom day.
 
If a workflow is launched using a calendar which does not contain the custom day specified for the Custom Day Choice, the following applies:

  • Run Criteria with the specified custom day will evaluate to false. If no other criteria was specified, the task will be skipped.
  • Skip Criteria with the specified custom day will evaluate to false. If no other criteria was specified, the task will not be skipped.
Note
titleNote

You cannot use a custom day defined as a period as part of the task run criteria.


Anchor
Complex
Complex
Complex

If enabled, the task runs or skips on the day(s) indicated in the Adjective, Noun, and Qualifier fields.

Anchor
Adjective
Adjective
Adjective

If Complex is enabled, you can use this field to specify which in a series of days you want to select. Used in conjunction with the Noun, Qualifier, and Nth Amount (if Adjective = Nth) fields. For example, to specify "the 15th business day of the month," select Adjective: Nth, Noun: Business Day, Qualifier: Month, Nth Amount: 15.
 
Options:

  • Every
  • 1st
  • 2nd
  • 3rd
  • 4th
  • Nth
  • Last

Anchor
Noun
Noun
Noun(s)

If Complex is enabled, you can use this field to specify the type of day(s) you want to select.

Used in conjunction with the Adjective, Qualifier, and Nth Amount (if Adjective = Nth) fields. For example, to specify "the 1st business day of the month," select Adjective: 1st, Noun: Business Day, Qualifier: Month.
 
Options:

  • Sunday through Saturday
  • Day = any day
  • Business Day = The business days specified in the calendar selected in the Workflow definition Default Calendar field.
  • Custom Days specified in the calendar selected in the Workflow definition Default Calendar field.

Anchor
Qualifier
Qualifier
Qualifier(s)

If Complex is enabled, you can use this field to specify the period(s) for your selection formula.

Used in conjunction with the Adjective, Noun, and Nth Amount (if Adjective = Nth) fields. For example, to specify "the 1st business day of the month," select Adjective: 1st, Noun: Business Day, Qualifier: Month.
 
Options:

Anchor
Nth Amount
Nth Amount
Nth Amount

If Adjective = Nth; Sequential occurrence of the day selected in Noun within the selected Qualifier.

Anchor
Adjustment - C
Adjustment - C
Adjustment

If Complex is enabled; Specification for adjusting a complex day by a less or plus number of days or business days.

Options:

  • -- None --
  • Less
  • Plus

Default is – None --

Anchor
Adjustment Amount - C
Adjustment Amount - C
Adjustment Amount

If Adjustment is Less or Plus; Number of days or business days to adjusting a complex day.

Default is 1.

Anchor
Adjustment Type - C
Adjustment Type - C
Adjustment Type

If Adjustment is Less or Plus; Type of day by which to adjust a complex day.

Options:

  • Day
  • Business Day

Default is Day.

Anchor
Variable
Variable
Variable

If enabled, instructs the Controller to run or not run the task, depending on the value of a specific variable. Used in conjunction with fields: Evaluate At, Name, Operator, and Value.

Anchor
Evaluate At
Evaluate At
Evaluate At

If Variable = enabled; Allows you to specify when you want the Controller to evaluate the variable.
 
Options:

  • Trigger Time -- Evaluate the variable when the Workflow is triggered.
  • Run Time -- Evaluate the variable when the task is about to run.
Note
titleNote

Evaluate At is applicable only to Variable criteria (it is hidden until the Variable field is enabled). Evaluate At has no impact on other criteria, which will resolve the same way whether the Evaluate At value is Trigger Time or Run Time; calendar-based criteria is always evaluated using the task instance Trigger Time (or the task instance Created time, if the workflow was launched manually).


Anchor
Name
Name
Name

If Variable = enabled; Specifies the name of the variable being evaluated. The variable does not need to exist when this record is created.

Anchor
Operator
Operator
Operator

If Variable = enabled; Allows you to select the operator to be used in the evaluation. Options: =, !=, >, >=, <, <=, regex (regular expression).

Anchor
Value
Value
Value

If Variable = enabled; Allows you to specify the value or regular expression (up to 255 alphanumeric characters) that the Controller should look for when evaluating the variable.

Buttons

This section identifies the buttons displayed above and below the Task Run Criteria that let you perform various actions.

Save

Saves a new record in the Controller database.

Update

Include Page
UC69IL:Update buttonUC69
IL:Update button

New

Displays empty (except for default values) Details for creating a new Database Connection.

Delete

Include Page
UC69IL:Delete buttonUC69
IL:Delete button

Refresh

Refreshes any dynamic data displayed in the Details.

Close

For pop-up view only; closes the pop-up view of this Database Connection.

...

Step 1

In the Workflow Monitor, right-click any white space in the Workflow Editor canvas.

Step 2

Click Insert Task.... The Task Insert > Task Selection dialog displays.

Step 3

Find the task you want to insert (see Searching For and Adding Tasks) and drag the task's icon onto the Workflow Editor canvas where you would like it to be inserted.

Step 4

The Task Insert > Predecessor/Successor Selection dialog displays.
 

Step 5

Select zero or more predecessors and zero or more Successors for the inserted task.

Step 6

By default, the inserted task will inherit the Trigger Time of the parent Workflow. If the Trigger Time of the parent Workflow is undefined, the Launch Time will be inherited as the Trigger Time instead. For task instances within an inserted Workflow, Run Criteria will be evaluated using the inherited Trigger Time.
 
If you do not want the inserted task to inherit the Trigger Time of the parent Workflow, de-select the Inherit Trigger Time field (by default, it is pre-selected).
 
For task instances within an inserted Workflow that did not inherit the Trigger Time of the parent Workflow, Run Criteria will be evaluated using the Created Time.

Step 7

Click OK. The Controller inserts the task as a successor to the selected predecessor task instance(s) and as a predecessor to the selected successor task instance(s)(s).

  • When the selected predecessor task instances complete, the inserted task will start to run, assuming that all of its dependencies (for example, virtual resources) have been met.
  • If the selected successor task instances had not already started, they will wait until the inserted task completes and all of their other dependencies have been satisfied.
Note
titleNote

Any predecessor task that is in a SUCCESS, FINISHED, or SKIPPED status will not prevent the inserted task from running.

 
For inheritance of actions on Defined status, refer to Universal Controller property Inherit Actions On Defined For Insert Task.

...

Step 1

From the Automation Center navigation pane, select Tasks > All Tasks or Tasks > Workflow Tasks.

Step 2

Display an Action menu either of three ways:

  • Right-click the Workflow in the All Tasks or Workflow Tasks list.
  • Open the Workflow and right-click in the Details.
  • Open the Workflow, click the Triggers tab, and right-click a Trigger on the list.

Step 3

Click Forecast... to display a Forecast dialog.
 

Step 4

Select a Date, Time, Time Zone, and Calendar for when you want to forecast the Workflow (and all of its sub-Workflows, if any).

  • If you selected Forecast from the All Tasks list, Workflow Tasks list, or Workflow Details, the default Calendar of the Workflow displays.
  • If you selected Forecast from the Triggers tab list, the default Calendar of the selected Trigger displays.

By default, the Time Zone field is read-only and displays the time zone in the Forecast Time Zone field, since the Use Forecast Time Zone field is checked.
 ;
The Forecast Time Zone field allows you to change what time zone this forecast of the Workflow will evaluate in. It defaults to the time zone of the Controller but can be modified to another time zone.
 
Uncheck the Use Forecast Time Zone field if you want to enable the Time Zone field and enter a different time zone.
 
The Forecast Time Zone and Use Forecast Time Zone fields allow the forecast to evaluate as if in one time zone, and also allow the Date and Time of the forecast to be based upon another time zone. The time zone associated with the Date and Time is used only for calculating the Date and Time at which the forecast starts.
 
For example, a Forecast could be executed to run at a specific date and time with respect to Time Zone, and yet the Forecast itself will execute, and evaluate Run Criteria and Execution Restrictions, based upon the Forecast Time Zone.

Step 5

Select a View in which you want to display the Forecast: Workflow or List.

Step 6

If you selected Workflow View, a Calculate Critical Path field displays. Enable/disable this field depending on whether or not you want to calculate the Critical Path of the Workflow.

Step 7

Click Submit to display the Forecast in the selected View.
 
Workflow View
 

 
In the Workflow View, each task has a Run Criteria evaluation label:

  • Run - Task border is gray and solid.
  • Skip - Task border is red and solid.
  • Not Evaluated - Task border is gray and dotted. (Run/skip criteria for this task is dependent on variable resolution; could not be evaluated.)

If you enabled Calculate Critical Path:

  • Task instances and connectors in the Critical Path display in the color specified by the Critical Path Color system property.
  • Run/skip criteria is resolved based upon the date specified in the Forecast option.
Note
titleNote

You can choose to show or hide skipped tasks in the Workflow View of the Forecast just as you can on a Workflow Monitor.

If Calculate Critical Path is enabled, skipped task instances are hidden, and the Show Skipped/Restore and Hide Skipped context-menu items are not available.

If Calculate Critical Path is enabled, but you want to see skipped task instances, you can restore the standard view by clicking the Toggle Critical Path View icon in the Workflow Forecast toolbar (see Workflow Editor Toolbar for a description of the tools in this toolbar).

 
The Workflow View lets you navigate into sub-Workflows (by double-clicking them) and back to the parent Workflow (via the Go to Parent icon).
 
 
List View
 

 